Passport Prime shipping dates

Timeline of communicated Prime ship targets (and pushes)

  1. End of March 2025 (original estimate)
    Foundation’s FAQ said Early Access units were estimated to ship at the end of March 2025. Foundation Docs
  2. Late April 2025 (push #1)
    On March 13, 2025, Foundation replied that Early Access devices would begin shipping in late April. Foundation Community
  3. “Over the next 3 weeks” from May 7 (push #2)
    On May 7, 2025, Foundation posted they expected remaining components to arrive over the next 3 weeks, and then they’d be able to assemble and ship the 1,000 Early Access orders (effectively shifting expectations into late May / early June). Foundation Community
  4. “Three weeks from today” from June 5 (push #3)
    On June 5, 2025, Foundation said they expected to begin assembling and shipping Early Access orders three weeks from that date (≈ late June). Foundation Community
  5. Week after July 24 (push #4)
    On July 2, 2025, Foundation gave a more specific schedule: assembly July 17, provisioning July 24, and shipping planned to begin the following week (≈ late July). Foundation Community
  6. No firm date as of July 31 (push #5)
    On July 31, 2025, Foundation confirmed Prime hadn’t shipped yet, was delayed, and they didn’t have a firm date (promising more detail in early August). Foundation Community

Count: how many times did they push the shipping date?

Based on these public statements, Foundation pushed Prime’s shipping expectation at least 5 times (from end of March → late April → late May/early June → late June → late July → then “delayed/no firm date”)